Register | Login | Set as Home Page | Bookmark | General Enquiries | Help | Tuesday, 14th of February 2012
Health & Safety Matters
 hsmsearch.com
Search 
Magazine 
Register for our ENewsletter
Click to visit http://www.toyota-forklifts.co.uk/EN/resources/Pages/default.aspx
What next?
 Request further Information    visit web site     Send to friend
 RVA Group company's profile
Click to visit http://www.casellameasurement.com

Poll : February
Spend on health & safety in your organisation in 2012 will be?
This is an anonymous poll for statistical purposes only
Last Month's Poll

Are you in favour or proposals to reduce the number of workplace safety inspections?

Yes - 25%

No - 75%

Follow Health & Safety Matters on Twitter

Going...going...gone
June 1st 2009

An increase in the number of large-scale decommissioning projects being undertaken is presenting a number of new safety challenges. Overcoming these challenges was part of the remit for RVA Group who recently oversaw the decomissioning and demolition of fertiliser manufacturer GrowHow's Severnside plant

As a result of the economic downturn a number of production facilities have been mothballed, rationalised or permanently closed down. This leaves those running them with a new challenge: the safe decommissioning – and in many cases dismantling and demolition – of facilities.

Even with the best intentions at heart, when money is tight the eye can come off the 'environmental and health and safety ball' and that is something no-one can afford – the global downturn doesn't mean hazards are less onerous, or that laws can be flaunted. Faced with conducting one of the largest UK industrial process plant demolition projects in recent years, the decommissioning team on GrowHow UK's Severnside site, near Bristol, ensured that safety was their number one priority.

In September 2007, premier fertiliser manufacturer GrowHow UK announced the decision to close its 100 acre Severnside plant, located on the eastern bank of the River Severn. From the outset, GrowHow recognised that a project of this magnitude required capabilities beyond their remit of expertise.

CDM co-ordinator and project management consultancy RVA Group was brought in at the end of 2007 to begin planning for the challenging processes that would follow the plant closures in April 2008.

In the extensive and highly complex 30-week programme that ensued, RVA supervised more than 60,000 man-hours of plant decommissioning, isolation and demolition by contractors EDS (Euro Decommissioning Solutions), regulating the clearance of facilities including nitric acid, ammonia, carbon dioxide and ammonium nitrate production plants, utilities equipment, laboratories and office buildings over nine separate locations within the site.

Hazardous materials

The practical challenges encountered on such large-scale decommissioning projects are substantial. For example, many areas of the process plants contain hazardous materials, whether they are corrosive, toxic or flammable, and often these substances have the propensity to become lodged in nooks and crannies. A great deal of attention therefore has to be deployed in preparing equipment and bringing it to a 'known state'. Striking the right balance for the cleaning regime is a vital aspect of the work; going beyond what is required can lead to avoidable operative exposure to hazards and unnecessary costs, not far enough and problems can then arise during dismantling and waste disposal activities.

The importance of getting this element of work fully documented and competently executed should not be underestimated.

However the complexities of the Severnside project presented a number of additional challenges. The deployment of traditional dismantling techniques throughout the project for example, was complemented by the controlled use of explosives to bring down the 100 metre tall Prill Manufacturing Tower, which once produced ammonium nitrate fertiliser pellets.

Speaking of the decision to use explosive engineering methods, RVA's operations director Ian Wharton explains: "The Prill Tower was a tubular reinforced concrete structure supported on 12 reinforced concrete legs, with process vessels mounted at the top, reached via an external lift shaft and attached staircase. It was too tall to demolish with conventional machinery, and the alternative of manually dismantling it piece by piece would have necessitated operatives working at height for extended periods of time. The health and safety risks associated with such a labour intensive option were simply unacceptable, and the fact that the 4,000 tonne tower has been in operational service for many years added to our concerns.

"We knew that the controlled use of explosives was the safest way forward but the fact that the tower had been the production centre for ammonium nitrate fertiliser prills created an added hurdle to overcome. Ammonium nitrate can itself, under certain conditions, become an energetic substance and hence has a potential to explode. If such a chemical residue was to be subjected to either significant impact – as would be experienced when the tower hit the ground during the demolition process – or was to come into contact with a heat source, there was a risk of secondary detonation and explosion. We therefore needed to eradicate any potential risks posed by the presence of ammonium nitrate, before a decision could be made.

How this was achieved

Taking samples from the structure and surrounding floor slabs to assess the degree of contamination in the concrete Holding joint consultations between RVA's explosives engineers and recognised experts to advise both in the properties of ammonium nitrate and theoretical explosives Leading a series of hazard study workshops so that each party had a complete understanding of the issues involved and could bring together their specialist skills and knowledge to mitigate any remaining risks Undertaking extensive decontamination of the internals of the tower and conducting a video inspection to validate the structure's cleanliness Managing the demolition contractor selection process and carrying out rigorous examinations of company structures, experience and safe working practices, to ensure required standards would be met.

Despite concluding that the level of risk posed was minimised, manageable and acceptable, RVA still incorporated into the dismantling contract the requirement for the appointed contractor (EDS) to engage an additional specialist explosives consultant to provide a secondary assessment and confirmation of their findings.

Put to the test

A test blast operation was completed two weeks prior to the blowdown to validate the design of the charge weight, drilling pattern and primary protection. Having removed one of the legs during the test blast, EDS devised a collapse mechanism – involving the removal by explosives of the remaining five legs – to ensure the tower would rotate and fall in a north easterly direction. The explosively charged legs were wrapped with several layers of chainlink mesh covered with geotextile fabric and additional specially fabricated restrained steel plating, to contain and minimise debris spread. A personnel exclusion zone ranging from 200 to 300 metres radius was established immediately prior to the blowdown.

After six months' of blowdown preparation in which RVA liaised with vibration specialists Vibrock, the National Grid and Severnside residents, the tower was reduced to rubble in less than 10 seconds, using 13kgs of explosives in 42 charge locations.

Speaking of the project's success to date, Ian explains: "Despite the complexities encountered, we have remained on schedule and within budget, and there have been no reportable or lost time accidents".

Ian continues: "In the current economic climate, organisations will understandably be focused on closing down their factories and plants in the most cost effective manner possible, due to the financial pressures that have led to the said situation. However they should not lose sight of the fact that decommissioning is not a straightforward process, and is certainly not something that can be rushed to achieve an accelerated exit. The fact that this undertaking was so successful is to a great extent because GrowHow actively acknowledged these factors.

"Co-operation has been key throughout and not just with external specialists. We recognised for example, how important it was to work with GrowHow's own experts in order to harness their invaluable knowledge. You cannot expect a skilled production engineer for example to become a qualified decommissioning engineer overnight, but when managing a facility decommissioning, the careful use of existing staff alongside experienced specialists is in most cases a positive move – no one knows the plant better than the people who have been running it.

"With an almost bizarre twist, preparing plant and machinery for dismantling and demolition can be less onerous than actually operating it throughout its life cycle, for example vessel entry may be avoided, working at height minimised and other inherently hazardous activities eliminated by the use of specialist decommissioning techniques, so long as the best team is assembled for the job, and the company is adequately prepared for the situation." RVA Group specialises in the decommissioning, decontamination, dismantling and demolition projects.